Transmission Line

SUMMARY

Out of 56 towers, 38 is erected. The foundation of the 51 towers is complete and other work is on progress. Two special towers were designed and procured as per the site need.

All materials required for the completion of the transmission line was ordered but due to increment in the cost of raw materials, the factory was not able to adhere to their timeline of delivery. Currently the workplan is on schedule for completion, but due to delay in supply of materials this could hamper the date of completion. At present the target to complete the transmission line is end of May 2022